DEVIATION
PREPARATION PROCEDURES
I
INTRODUCTION
A.
Scope
This
procedure establishes a method, procedure, and the controls to effectively and
efficiently deviate from approved procedural documentation.
B.
Application
This
procedure is applicable for all SITS and Aircraft Test Procedures, Configuration
Checklists, Pre/Post Flight Checklists, and all other similar procedural
documentation.
C.
Responsibilities
All
Pt. Mugu Operations, Functional Departments.
II.
GENERAL PROCEDURE
A.
Background
Detailed
procedures are developed, published and approved for use in order to maintain
test discipline, ensure complete and comprehensive instructions to test
personnel and to permanently record
test results. Once the initial document is approved there exists no official
method to make real time corrections, changes or alterations short of a complete
revision cycle. This situation is neither efficient nor cost effective.
B.
Purpose
This
procedure provides the capability and authority for lead test personnel to
officially record deviations to test documentation in order to expedite test
completion, maintain configuration control of the affected document, and to
satisfy [company] and Navy quality requirements.
C.
Deviation Preparations Procedures
l.
The test conductor/lead engineer will initiate a deviation sheet and associated
instructions, whenever the test or functional instruction is deemed by him to be
in error or cannot be accomplished as written.
Note:
Deviations are not required for obvious typographical errors or minor
"pen/ink" corrections.
2.
The test conductor/lead engineer will "red line" the portion of the
procedure to be deleted or modified.
3.
[Company] Quality Control will annotate the procedure with the deviation number
in the left margin and indicate the step has been performed as modified by
affixing his stamp to the deviation sheet in the space provided and in the left
margin of the procedure in the near vicinity of the deviation number (back
stamp).
4.
Navy Quality Control will co-stamp, as required, the procedure and/or the
deviation sheet.
5.
[Company] Quality Control will maintain a copy of the deviation sheet(s) with
the official as‑run copy of the test document.
6.
The test conductor/lead engineer will process the deviation sheet original
through review by the document originator and the applicable Project Engineer.
Note:
Deviations to procedures not part of an ACCB package can be approved by the
Project Engineer and the Engineering Manager/Director.
7.
The deviation sheet original is then forwarded to the GACCB chairman for
approval and forwarding on to the Navy ACCB for final approval.
Note:
GACCB and Navy ACCB review is required only for those documents which are part
of an approved ACCB package.
8.
Navy ACCB will either approve the deviation or return the document with comments
and a disposition.
If
the document deviation is approved:
The
ACCB will return the original signed deviation to the GACCB chairman for
internal [company] distribution.
If
the documented deviation is not approved:
The
ACCB will return the deviation with appropriate comments to the GACCB chairman
for coordination, resolution and re‑submittal.
9.
[Company] Quality Control will coordinate with Navy Quality Control the final
close-out of all associated work orders, MAF's, etc. The ACCB approved deviation
becomes a permanent part of the official "as‑run" data package.
10.
The test document originator will maintain a file of all approved deviations
against his procedure. If and when the procedure is updated or revised all
permanent deviations will then be incorporated. If the number or magnitude of
deviations become excessive this will cause the originator to generate an update
or revision.
11.
Data Management will, upon receipt of an ACCB approved deviation, maintain that
deviation in the master file attached to the document original.