SITS
TESTING RESPONSIBILITIES
I.
INTRODUCTION
A.
Scope
This
document states the SITS testing responsibilities according to specific task and
department at Point Mugu Operations.
B.
Application
This
procedure applies to SITS testing at Point Mugu, California.
C.
Responsibilities
-
Engineering Department
-
Flight Test Department
-
Manufacturing
-
Quality Control
D.
Definitions
- A/C: Aircraft
- ENG'G: Engineering
- FLT TST: Flight Test
- MFG: Manufacturing
- MOD: Modification
- PMTC: Pacific Missile Test Center
- SITS: System Integration Test
Station
- SOF: Safety of Flight
- WRA: Weapon Replaceable Assemblies
II.
GENERAL PROCEDURE
A.
Background
The
System Integration Test Stations (SITS) at Pt. Mugu California is a simulation
facility used to integrate and test F‑14 aircraft systems ant operational
flight software. Computer support equipment provide aircraft environmental
inputs to a mock‑up version F‑14 where flightworthy hardware and
software are tested and verified. The SITS testing responsibilities which are
divided among the Engineering, Manufacturing, Flight Test and Quality Control
departments are outlined in [company document]
B.
Task Breakdown
-
SITS Scheduling
This
task is performed by the Engineering department in coordination with Navy
personnel at PMTC. SITS lab time requests are submitted by the user one week in
advance of planned testing along with special lab support utility requirements,
if any. SITS lab schedule is generated in cooperation with PMTC where testing
priorities are established. SITS lab schedules are produced weekly and
distributed to all personnel.
Engineering
personnel utilizes the SITS frame for testing and development at assigned time
intervals unless alternate arrangements are made through the coordinator prior
to the scheduled frame time.
-
SITS Modification Functional Procedures
The
procedures are drafted by the Engineering department if an addition or
modification is made to the SITS frame. These procedures include step by step
instructions that test the operation of the modification as an individual unit
as well as its impact on the total system operation.
-
SITS Modification Installation and Checkout
Modification
is performed by the Manufacturing department. The modification is verified as
operational and as adhering to specifications by Manufacturing with the support
of Engineering. Quality control witnesses a retest of the functional checkout
ant verifies modification as required.
-
SITS Developmental and Integration Test
Testing/troubleshooting
is performed in the SITS laboratory with support equipment simulating various
aircraft and environmental conditions. Engineering or flight test develops and
tests new software in SITS and verifies the operation of weapon replaceable
assemblies (WRA s) and their interfaces.
-
SITS Safety of Flight Tests
Testing
is performed in the SITS laboratory by certified Engineering personnel on
software development tapes and existing baseline tapes prior to aircraft
testing. Engineering schedules the SITS frame and executes test.
-
SITS Support of Aircraft Tests
This
task allows communication between the aircraft either on the ground or in flight
and the SITS laboratory. Flight test and engineering configure SITS to enable
the communication and conduct tests from the laboratory or on the aircraft.
Support equipment records data and provides necessary simulated inputs.